information-major-works
October 25, 2018
Information

Major Works Information | Members & Guests

Dear members and guests,

The Ian Thorpe Aquatic Centre will be undergoing major works of all internal staircases and a new external gym entrance.

The estimated time frame of works will be from the 5th of November to the 8th of April 2019. During this time, ITAC will continue to run as normal with minimal disruptions. All construction will be done after hours.

Construction will be done in three phases with the estimated times as follows:

Phase One:

5th November – 21st December
Modification of stairs 2, 3, 4, 5 & 7

Phase Two:

7th January – 1st February
Gym entrance and reception desk

Phase Three:

4th February – 8th April
Modifications on Stairs 1 & 6

Please see the map below to reference each phase of work. If you have any further questions, please contact our friendly team on 02 9518 7220.

Kind Regards,

ITAC Management

Information-major-works